In Switzerland, where quality and thoroughness traditionally take precedence over speed, building a house is a complex undertaking. The construction time is not a fixed quantity, but rather the result of an equation with many variables. Basically, you need to distinguish between the actual construction phase (groundbreaking to move-in) and the entire project phase (idea to move-in). While the excavators often only operate for 6 to 12 months, the bureaucratic preparation can consume almost as much time. Anyone wanting to calculate a realistic house construction time must consider Swiss federalism, the weather, and the construction method. In this article, we break down the timeline in detail and show you where the time-wasters lurk and how you can optimize your house construction time .
Egal, welche Fragen du rund um Immobilien hast – Loft ist da, um sie dir übersichtlich, verständlich und zuverlässig zu beantworten.
Stelle Fragen zu einer ImmobilieBefore the first brick is laid, a lot of time is spent at the desk. This phase is often forgotten when calculating the construction time of a house .
Now the visible construction phase of the house begins .
This phase of the house construction is extremely weather-dependent . A harsh winter or prolonged rain can set the schedule back by weeks.
This is often the longest phase of a house's construction . From the outside, the house looks finished, but inside there is a great deal of activity.
A major factor influencing the construction time of a house is the choice of construction method.
This is the Swiss classic. The construction time for a house here is the longest, as materials like concrete and mortar need time to dry.
Here, walls are pre-produced in the factory and only assembled on the construction site.
Why does it often take longer than planned?
An efficient construction time for a house saves money.
answer the question "How long does it take to build a house ?", here is a typical calculation for a single-family house built using solid construction methods:
Total project duration: 12 to 20 months.
Pure construction time for the house (from groundbreaking): 8 to 12 months.
construction time on site is often reduced to 3 to 5 months, while the planning phase remains similarly long.
The construction time for a house is a dynamic process. For a typical detached house in Switzerland, you should expect approximately 9 to 12 months from groundbreaking to moving in. If you include the planning and the often lengthy permitting process, you can easily reach a total duration of 1.5 to 2 years.
Those under time pressure should consider a prefabricated house or buying an existing property. However, those building a custom home need patience. A shorter construction time should never compromise quality – drying times are physical laws, not recommendations. A realistic estimate of the construction time is the best protection against financial stress.
If you are looking for support in finding the right plot of land or want to know how the location could affect your project, it is worth using Loft 's analyses to put your planning on a solid basis.